KeFax Course Enquiries

Distribution System Design & Planning 

5 Days

 Day One

  

D1.P1.1           General Principles of Planning

      Objectives

      Premises

      Alternatives

      Evaluation

      Decision Making

      Implementation

 

DI.P1.2            Primitive Anatomy of Distribution System

 

D1.P1.3           General Principles applied to Distribution Planning

 

DI.P1.4            The Distribution Design & Planning Process

      Technical Design

      Physical Planning

      Costing

      Terms & Condition, Connection Agreements

      D & P Programme

 

BREAK

 

D1.P2.1           Technical Design

      Thermal Ratings

      Voltage Regulation

      Quality of Supply

      Excess Current and Earth Fault Protection

      Calculations and Models

 

D1.P2.2           Design Calculations Part 1

      Low Voltage Regulation (volt drop) – 3 Phase – Single Phase

      ADMD

      Loss of Diversity

      Unbalance Factors

 

D1.P2.3           Primitive Model Update

 

LUNCH

 

D1.P3.1           The Distribution Code

      Mandatory

      Distribution Planning & Connection Code (DPC)

      Distribution Operating Code (DOC)

      Distribution Data Registration Code (DDRC)

 

Day One (continued)

 

D1.P3.2           Quality of Supply

      Annex 1 of Distribution Code

      E.R.P. 28   – Planning Limits for Voltage Fluctuations

      E.R.G 5/3  – Limits for Harmonic Distortion

      E.R.P. 29   – Planning Limits for Voltage Unbalance

      E.R.P. 2/5  – Security of Supply

 

D1.P3.3           Technical Design Safety Issues

      Annex 1 of Distribution Code

      Fault Levels

      Earthing Issues at Substations including rise of Potential

 

D1.P3.4           C.D.M. Issues

 

BREAK

 

D1.P4.1           Exercise/Worked Example

 

 

***************

Day Two

 

D2.P1.1           System Voltage Regulation & Control

      Voltage Limits

      Voltage Control by AVR Devices

      Voltage Control by Planning Limits

      Allocation of available Band-width

      Primitive Model Update

 

BREAK

 

D2.P2.1           Design Calculations Part 2

      Low Voltage Regulation on Rural Networks

 

D2.P2.2           Design Calculations Part 3

      Voltage Fluctuations (flicker) using the methods in E.R.P.28

 

D2.P2.3           Worked Examples

      P28 using Single Phase Low Voltage Resistive Load

      P 28 Motor Start Example

 

LUNCH

 

D2.P3.1           Physical Planning

      Route Selection

      Site Selection

      Planning Consents

      Wayleaves

      Designated Areas

      The Modern Predicament

      C.D.M.

      Work Planning

 

D2.P3.2           Costing

      Standard Cost Estimating

      Prime Cost for Material and Labour hours

      Overhead Cost Recovery

      Repairs and Maintenance Costs

      Computerised Estimating Schedule

      Basic Schedule on Spreadsheet (Logistics)

      Budget Quote for non-standard items

 

BREAK

 


 

Day Two (continued)

 

D2.P4.1           Plant Ordering

      Specification

      Competitive Tenders

      Lead Times

 

D2.P4.2           Exercise

 

 

 

 

***************

 


Day Three

 

D3.P1.1           Network Modelling

       Review of Primitive Model

 

D3.P1.2           The Percentage Impedance and Per Unit (pu) Method

       Common Base

       Voltage Levels

       Useful Expressions

 

D3.P1.3           Circuit Models

 

D3.P1.4           Transformer Models

      Impedance Models

      AVR

 

D3.P1.5           Flesh on the Primitive Model

 

BREAK

 

D3.P2.1           Design Calculation Part 4

       High Voltage Regulation & Control

       Worked example

 

D3.P2.2           Introduction to Fault Levels

      Through-fault Currents and their Magnitude

      Synchronous Fault Level

      Fault Levels expressed in MVA or kA

      Design Limits and typical values on the Primitive Model

      Types of Fault

 

D3.P2.3           Exciting the Primitive Model

      Fault Level expressed as Impedance (with voltage behind)

      X/R values

      Driving the Primitive Model

      Let’s not call it Primitive any more

 

LUNCH

 

D3.P3.1           Design Calculations Part 5

      Simple (balance 3Ph) fault level calculation

      Worked example

 

D3.P3.2           Unbalanced Faults

      Commentary only on method of network sequence components

 


 

Day Three (continued)

 

D3.P3.3           Voltage Unbalance

      E.R.P29 again

      Expressing Magnitude of Unbalance

      Useful (approximate) Calculation Technique

 

BREAK

 

D3.P4.1           Switchgear Rating

      Circuit Breaking Duty

      Circuit Making Duty

      Transient Fault Level

      Spinning Load

      IEC 909

 

 

 

***************

 

 


Day Four

 

D4.P1.1           Terms & Conditions Part 1

      Define Objectives with Customer and Quantify

      Charges related to MD and Allowances

      Contracted Period

      Agree Level of Security being offered to Individual Customer

      Discuss and Adopt Realistic Programme Date early on

      Offer Various Alternatives

      Agree Payment Stage(s)

      Continually review progress through D&P Process Programme

 

D4.P1.2           Terms & Conditions Part 2

      Developments in the Connections Business

      Competition

      Point of Connection

      Existing Circuit Capacity

      Contestable Connection work

      Non-Contestable work

      Approved Installers (Lloyds Register)

      Joint Construction & Adoption Agreements

      Know the Distribution Code before saying ‘No’

      The Connection Liaison Role

      Design Approval

      Specification

 

BREAK

 

D4.P2.1           Security of Supply

      Alternative Supplies

      Reliability Studies

      Summary of E.R.P. 2/5

 

D4.P2.2           Protection Studies

      Basic Protection

      Fault Level throughout Network

      Protective Device Settings for Discrimination

      Through Fault Duty on Components

 

D4.P2.3           Earthing

      Reference to Earth Mandatory – Supply Regs

      HV Networks – single point reference

      LV Networks – multiple point earthing

      Common HV/LV earth

      Earth electrodes – Soil Resistivity – Resistance to Earth

      Earth Fault Loops – HV and LV


 

Day Four (continued)

 

      Limiting Magnitude of Earth Fault Current

      Rise of Potential at Substations – Hot sites

      Step and Touch Voltages

 

D4.P2.4           Worked Examples

      Rise of Potential during HV Fault

      Earth Fault Current in Transformer LV tails

 

LUNCH

 

D4.P3.1           Network Losses

      Variable

      Fixed

      Magnitude

      Cost

 

D4.P3.2           Capital Appraisal

      Cash Flow

      Pay Back Period

      Present Worth

      DCF

 

D4.P3.3           Worked Example

      Appraisal of Competing Options

 

BREAK

 

D4.P4.1           Review of Design Calculations Required

      Voltage Regulation and Control – can be an iterative process

      Load Sharing of Parallel Circuits – messy by hand above two circuits

      Loss Calculation – very messy by hand over extended irregular load distribution

      Thermal Loadings

      Fault Level Studies for Symmetrical and Asymmetrical Faults

      Connecting Impedance

      Reliability Studies

 

D4.P4.2           Digitised Network Models

      DINIS

      Instant Access to Models of Existing Network

      Easy Construction of Option Models

      High Level Mathematical Equations solved for you


 

Day Four (continued)

 

      Rapid Solutions

      But you need to understand power systems before you can use it!

      If you ain’t got DINIS

      Spread Sheet Models soon pay back set-up effort

 

 

***************

Day Five

 

D5.P1.1           New Connections

      Determination of Point(s) of Connection

      Capacity of existing (adjacent) Circuits

      Ring-fencing Connection from Reinforcement

 

D5.P1.2           New Housing Estates

      ADMD

      Substations – number and location

      HV Network

      LV mains & services: Remember Protection, Flicker, Thermal & Regulation (PFTR)

      Xmas Trees

 

D5.P1.3           Exercise – Worked Example

 

BREAK

 

D5.P2.1           Industrial Connections

      Review Terms & Conditions

      Review Quality of Supply Issues

      Review Security of Supply Issues

      PFTR as always

      Fault Level Contribution from Spinning Load

      Joint use Substations and Switchboards

      Ownership Boundary

      Control Boundary

      ET

 

D5.P2.2           Exercise – Worked Example

                       

LUNCH

 

D5.P3.1           Network Reinforcement (and asset replacement)

      Need to Monitor Network Performance and to keep pace with load growth and age

 

D5.P3.2           Identifying Reinforcement Requirements

      Load Planning Estimates used as Overview

      Automatic Data Collection (SCADA) and Alarms

      Add Load Enquiries

      Voltage Complaints

      Quality of Supply Complaints

      Interruption to Supply Complaints

      NAFIR Reports

      Local Plans published by Local Authorities

 

 

Day Five (continued)

 

D5.P3.3           Worked Example and Discussion

 

BREAK

 

D5.P4.1                       COURSE REVIEW

 *********************** ********************************

[Home] [Electrical Power Training] [Engineering competence management software] [Generation Transmission Distribution skills development] [Power industry professional learning support] [Short term contractor agency] [Utility Engineer skills databases] [Helpline] [Course List] [Links]